Some Navy subs are waiting years for shipyard work, and that’s costing billions of dollars

Maintenance delays have cost the Navy’s attack submarine fleet more than 41 years they could have been in operation—and those waiting to be taken out of service could cost more than $3 billion over the next five years, according to a recent watchdog report. The main problem is that shipyards are simply overloaded with work, the Government Accountability Office wrote in an Aug. 27 report. “The USS Pasadena entered inactive idle status on January 1, 2025 and is not expected to be inducted" into Puget Sound Naval Shipyard "for decommissioning until November 15, 2028 (1,414 days)—due to shipyard capacity constraints,” the report said. “During this time, the attack submarine is unable to be
…