Defence projects to start only when fully funded, NAO says
The Ministry of Defence has told its teams that work on some projects can only start once funding for the whole project is available, in a bid to end a culture of approving business cases on the basis that affordability would be resolved later, according to the National Audit Office. The NAO’s report states: “The MoD intends to mitigate cost growth by strengthening its system for approving project proposals. Internal guidance on implementing the DIP, issued in July 2026, states that some investment decisions would be sequenced by priority and work could only be started when funding for the whole project was available. This was to address a culture within the MoD whereby it approved business
…